Our team created plans to reduce spill risk at the John Deere Harvester works facility by eliminating unnecessary piping and adapting infrastructure to operate with the proposed changes.
Semester of Project:
Team Photo:

Our team created plans to reduce spill risk at the John Deere Harvester works facility by eliminating unnecessary piping and adapting infrastructure to operate with the proposed changes.
Problem Statement
Team 21 was tasked with attending to the air-cooled-chilled-glycol system at the John Deere Harvester Works Facility in East Moline, IL. The chilled glycol system supplies several workstations around the facility, linked by a large piping network. As the
Project Poster
Download the Project PosterProject Presentation Video
Project Demonstration Video
Our team created plans to reduce spill risk at the John Deere Harvester works facility by eliminating unnecessary piping and adapting infrastructure to operate with the proposed changes.